Project : FACULTY OF ENGINEERING – CHINESE UNIVERSITY
Location : Cairo, Egypt (Under Construction)
Owner : Chinese University of Egypt
Client : Progress Consulting Group
Description : The project is the faculty of engineering of the newly established Chinese University in Egypt. The project is located at Cairo with a total land area of 25000m2 & built up area around 20000m2. The project consists of the following buildings:
1- Main hall building with 2 main halls for lectures.
2- Administration building with 3 floors.
3- Teaching classes building with 3 floors.
4- Laboratory & workshop building with 3 floors.
5- Students affairs building with 3 floors.
6- Substation, Mosque, & canteen & other related service buildings.
The total connected power is around 5 MVA.
Scope of work: Design for phase 3 buildings & related site networks for all MEP installations in building & site.

Work Shop Drawings for phase 4 buildings & related site networks for all MEP installations in building & site.